Use forward and backward pass to determine project duration and critical path

By Engineer4Free on youtube.com

More about this content:

In this video, you'll learn to determine the project duration and critical path of a project. The process involves creating a rough draft of the project and then doing a forward pass and backward pass to get the early start and late start times. The critical path is determined by finding which activities have the same early finish and late finish times. Delaying activities on the critical path will increase the duration of the project, while delaying activities off the critical path will not affect the duration.